Project Case: Read, invent and incorporate information where necessary.
You have recently been recruited as the Project Manager to develop an ERP used by a big Multinational Company for storing all of their information of business clients, employee, sales etc. To complete the project your team of 8 members of different skills would get 3 months.
1. a. Some project development activities are given below for the case above. Complete the chart with 2 more activities with time, predecessors. [Marks-3]
Activities | Duration (in Day) | Predecessors
A. Primary Plan | 5 | None
B. Defining Requirement | 6 | None
C. Resource Procurement | 8 | None
D. Design | 10 | A,B
E. Train Resources | 6 | C
F. Development | 25 | D,E
G. Testing | 12 | F
H. | -- | F
I. | -- | --
b. Using your answer of question 1, draw an AOA (Network Diagram) for your list of 9 activities. Find the critical path. [Marks-5]
2. c. Figure out a solution using any quality improvement tool if your primary releases are less standard to clients. [Marks-4]
d. Distinguish between i. EV vs PV and ii. CV vs SV in costing. [Marks-7]