System Analysis and Design
CSE · Quiz · Fall 25
Paper 2 of 7Section 66_C · Md. Ferdous Foysal Hridoy (1)Switch
Section 66_C
Paper 2 of 7
Read the questions as text
Read off the PDF by AI, so it may have mistakes. The PDF is the original.
Daffodil International University
Department of Computer Science and Engineering
Faculty of Science and Information Technology (FSIT)
Class test3, Semester: Fall-2025
Course Code: CSE227
Section: 66_C
Course Title: System Analysis and Design
Course Teachers: Dr. Md. Monzur Morshed (MMM)
Time: 50 min
Total Marks: 15
[Answer all the questions]
1. The following table shows a list of activities/tasks, their independencies and times required to complete each activity/tasks for a project:
Activities/Tasks | Dependency | Time(Week)
A | - | 10
B | - | 5
C | - | 7
D | A, B | 7
E | C | 6
F | E | 4
G | D, F | 10
H | G | 4
I | G | 9
J | H, I | 10
(a) Draw the Gantt chart, PERT Network and show ES, EF, LS LF times.
(b) Find the critical value.
(c) Find the slack times
[9]
1. Cox'sbazar is a tourist place in Bangladesh that has the longest sea beach, many sites, along with forests and striking mountains. A few first-class hotels and many less-expensive accommodations can be found along its beautiful sand beaches. The major airlines have regular flights to Cox'sbazar, as do several small airlines. Tourist authority wants to increase tourism and develop new markets for sea fish and tropical agricultural products.
(a) What Internet business model would be appropriate? What functions should the Web site perform?
(b) Select any two electronic payment systems for the business and explain the working procedure for this case.
[3+3]