Software Project Management and Documentation
SWE · Midterm · Fall 26
Paper 2 of 2Batch 40Switch
Batch 40
Paper 2 of 2
Read the questions as text
Read off the PDF by AI, so it may have mistakes. The PDF is the original.
Daffodil International University
Faculty of Science & Information Technology
Department of Software Engineering
Midterm Examination; Fall-2026
Course Code: SE 411; Course Title: Software Project Management & Documentation
Sections 40 (A - H) Teachers: MKS, DSM, MSI
Time: 1:30 Hrs
Marks: 25
Answer ALL Questions
[The figures in the right margin indicate the full marks and corresponding course outcomes. All portions of each question must be answered sequentially.]
Case Study: AI-Based Smart Hospital Management System
Read the case carefully. You may invent and incorporate additional information wherever necessary.
You are appointed as the Project Manager of a software company that has received a contract to develop an AI-based Smart Hospital Management System for a chain of hospitals operating across Bangladesh. The project duration is 6 months, and the budget is limited with very little contingency reserve.
The client expects an integrated solution including:
Electronic Health Records (EHR),
Online Appointment Management,
AI-assisted Disease Prediction,
Pharmacy and Inventory Management,
Billing and Insurance Processing.
The project team consists of 2 Systems Analysts, 4 software engineers, 2 UI/UX designers, 2 QA engineers, 1 database administrator and few support staff. While the development team is technically competent, most members have little experience working on healthcare software and AI applications. Several stakeholders are involved, including hospital directors, doctors, nurses, IT administrators, insurance companies, government regulatory authorities, and patients. Some stakeholders have conflicting priorities. Doctors demand usability and speed, while management is primarily concerned with cost and compliance.
As the project manager, you are allowed to select suitable management approaches, communication methods, quality assurance techniques, procurement strategies, and motivational practices to ensure successful project completion.
1. a. Draw a WBS for the above project so that it can be easily controlled. [Marks- 3] [CO-1 Level-3]
b. Predict the challenges for the given case study (project). [Marks- 3]
2. a. In a predictive project development, some activities are given below. Optimize the following chart filling the dash spaces (----) with Duration, Predecessors and make the list complete. [Marks- 2] [CO-2 Level-4]
Activities | Predecessors | Duration (in Day)
A. | None | 8
B. | A | 15
C. | A | 12
D. | A | 15
E. | B | 10
F. | C,D | 30
G. | E,F | ----
H. | G | 12
I. | G | 8
J. | ----- | 10
K. | ----- | ----
b. Now following answer of question 2.a. correlate the information to a Network Diagram for all 11 activities. Identify the critical path. [Marks- 6+1=7]
c. Identify cash flow for the following information. [Marks- 5]
Year -> | 0 | 1 | 2 | 3
Amount in $ | | | |
Investment | 200,000/- | 20,000/- | 25,000/- | 25,000/-
Income | 30,000/- | 85,000/- | 95,000/- | 85,000/-
Interest Rate | 6% | 6% | 5% | 5%
Cash Flow | | | |
d. Select one quality issue from the given case and analyze your issue following any quality improvement tool to solve it. [Marks- 5]