Software Project Management and Documentation
SWE · Quiz · Summer 26
Paper 8 of 8By Md. Mehedi Hasan (2)Switch
Paper 8 of 8
Read the questions as text
Read off the PDF by AI, so it may have mistakes. The PDF is the original.
Daffodil International University
Faculty of Science & Information Technology
Department of Software Engineering
Course Code: SE411, Course Title: Software Project Management & Documentation
Quiz 3: Section: 44_I Time: 30 Minutes
Smart Disaster Response and Emergency Management System
A private university plans to develop a Smart Campus Management System to improve campus operations and student services. The proposed system will integrate smart attendance, classroom and laboratory booking, campus security monitoring, mobile notifications, transportation tracking, digital payment, and real time facility management.
The university has approved a 10 month implementation period with a fixed budget. The project involves students, faculty members, administrative officers, security personnel, transport operators, software developers, hardware suppliers, payment service providers, and university management. The project team has limited experience integrating IoT devices and third party payment services. The university also needs the system to remain available during peak registration and examination periods.
a) Conduct a SWOT Analysis of the Smart Campus Management System and justify whether the university should proceed with the project. [5 Marks]
b) The project manager is evaluating three options for procuring the required computing infrastructure:
Option | Initial Cost | Monthly Operating Cost | Maintenance Cost | Salvage Value
On Premise Server | $80,000 | $4,000 | $3,000/month | $25,000
Public Cloud | $8,000 | $18,000 | Included | $0
Hybrid Infrastructure | $45,000 | $10,000 | $2,000/month | $12,000
The project duration is 10 months.
Calculate the total procurement cost of each option and recommend the most appropriate option considering cost, reliability, scalability, and the project deadline. [5 Marks]
c) Prepare a Communication Management Plan showing how project information will be communicated among university management, faculty members, students, developers, suppliers, security personnel, and other relevant stakeholders. Include the stakeholder, information, communication method, frequency, and responsible person. [5 Marks]